Utility Work and Excavation
Welcome to the City of Taunton Department of Public Works &
Office of Mayor Thomas C. Hoye, Jr. Utility Work & Excavation Page!

WEEKLY UTILITY WORK UPDATE
Thank you for visiting this page.   There are a number of ongoing projects happening throughout the city. Many of the current improvements are critcal to our city's aging infrastructure,  and are a sign of progression.  The information on this site is to help residents and visitors carry out their normal activities and avoid traffic during the "high construction" season.

To report a pothole, please call the DPW at (508) 821-1431.  For more information on potholes or how to fill out a claim related to motor vehicle damage caused by a pothole please click here.

If you have any questions pertaining to the projects taking place, please call the Department of Public Works (DPW) at (508) 821-1431.  If you have any questions referring to this site, please call the Mayor's Office at (508) 821-1000.

The following construction work will be occurring in Taunton for week ending Friday 06/12/15:

Sewer/Drain
Bay St (Jackson St to Whittenton St) – replacement of drain manholes
Weir St (Mill River to High St) – CIPP lining of drain pipe (no excavation)
Trescott St - CIPP lining of drain pipe (no excavation)
Washington St @ N. Pleasant St - CIPP lining of drain pipe (no excavation)
N. Pleasant St @ Washington St - CIPP lining of drain pipe (no excavation)

Water
No work planned.

Gas
Friend St – excavated gas service replacement
Sheridan St – excavated gas service replacement

Paving/Sidewalks
No work reported

Cable (Comcast)
None

Verizon
Washington St at Mill River Bridge

TMLP (Electric)
No work reported.

Bridge Construction
No bridge closures are anticipated.


The following construction work will be occurring in Taunton for week ending Friday 06/05/15:

Sewer/Drain
Weir St (Mill River to High St) – CIPP lining of drain pipe (no excavation)
Trescott St - CIPP lining of drain pipe (no excavation)
Washington St @ N. Pleasant St - CIPP lining of drain pipe (no excavation)
N. Pleasant St @ Washington St - CIPP lining of drain pipe (no excavation)

Water
No work planned.

Gas
Friend St – excavated gas main replacement
Sheridan St – excavated gas main replacement

Paving/Sidewalks
No work reported

Cable (Comcast)
None

Verizon
Washington St at Mill River Bridge

TMLP (Electric)
Washington St @ Mill River Bridge – installing and splicing underground cables (all week).

Bridge Construction
No bridge closures are anticipated.

The following construction work will be occurring in Taunton for week ending Friday 05/29/15:

Sewer/Drain
Kilton Place – excavated installation of new sewer pipe.
Kilton St (near Kilton Place) – excavation to abandon existing cistern
Weir St (Taunton Green to High St) – CIPP lining of drain pipe (no excavation)

Water
No work planned.

Gas
Friend St – excavated gas main replacement
Sheridan St – excavated gas main replacement

Paving/Sidewalks
No work reported

Cable (Comcast)
None

Verizon
Washington St at Mill River Bridge

TMLP (Electric)
Washington St @ Mill River Bridge – installing and splicing underground cables (all week).

Bridge Construction
No bridge closures are anticipated.


The following construction work will be occurring in Taunton for week ending Friday 05/22/15:
Sewer/Drain
Kilton Place – excavated installation of new sewer pipe.
Dana St (@ Morton St) – excavation near manhole for sewer service replacement, & CIPP lining of drain pipe.
Hill St – CIPP lining of drain pipe (no excavation)

Water
Court St – installation of water services.

Gas
Friend St – excavated gas main replacement
Sheridan St – excavated gas main replacement

Paving/Sidewalks
No work reported

Cable (Comcast)
None

Verizon
Washington St at Mill River Bridge

TMLP (Electric)
Washington St @ Mill River Bridge starting Monday 5/18/15, installing underground cables thru our manholes and new duct system.

Bridge Construction
No bridge closures are anticipated.








9102012_104257_0.png

452013_103049_0.jpg